# S12 — Asynchronous feedback for scheduling
|
||||||
|
|
||||||
|
Status: REFINED
|
||||||
|
|
||||||
|
Agreed after the grill-me interview; shared understanding confirmed.
|
||||||
|
|
||||||
|
## User story
|
||||||
|
|
||||||
|
As a dance-school maintainer, I want feedback after starting Schedule Groups,
|
||||||
|
so that I can see whether the backend is still calculating, when it finishes
|
||||||
|
and what the outcome is, including when I leave and return to the show page.
|
||||||
|
|
||||||
|
## Background execution and concurrency
|
||||||
|
|
||||||
|
- Start scheduling in the backend without keeping the initiating HTTP request
|
||||||
|
open until the calculation finishes. Navigation, page reloads and disconnected
|
||||||
|
clients must not stop the calculation.
|
||||||
|
- The backend owns the current scheduling status for each show. All open
|
||||||
|
screens see the same status, including screens that did not start the run.
|
||||||
|
- Allow at most one active calculation per show. Disable Schedule Groups while
|
||||||
|
it is running and reject duplicate starts in the backend as well.
|
||||||
|
- Different shows may calculate concurrently. A global capacity limit and a
|
||||||
|
waiting queue are outside S12.
|
||||||
|
- Retain the existing 30-minute solver limit and scheduling rules.
|
||||||
|
|
||||||
|
## Progress and outcomes
|
||||||
|
|
||||||
|
- While running, show elapsed time, the current optimization phase (attendance,
|
||||||
|
spread or variety), and whether a valid solution has been found.
|
||||||
|
- Report a valid solution as soon as the solver discovers one, including during
|
||||||
|
a phase. Extend solver progress reporting rather than waiting for the phase
|
||||||
|
to finish. Do not apply intermediate solutions.
|
||||||
|
- Do not present a completion percentage or estimated finish time: the phases
|
||||||
|
do not represent proportional parts of the calculation time.
|
||||||
|
- Keep the latest status and outcome per show until a new calculation starts.
|
||||||
|
Show the finish time and distinguish an optimal solution from a valid solution
|
||||||
|
whose optimality was not proven within the time limit.
|
||||||
|
- For a successful result, show a concise summary with concrete results for
|
||||||
|
attendance, spread and variety, using understandable labels.
|
||||||
|
- Clearly distinguish invalid input, infeasibility, solver failure, time limit
|
||||||
|
without a valid solution, rejection because inputs changed, and interruption
|
||||||
|
by a backend restart. Explain why no result was applied and that existing
|
||||||
|
assignments were preserved.
|
||||||
|
|
||||||
|
## Applying results
|
||||||
|
|
||||||
|
- Retain the confirmation before starting that explains replacement of existing
|
||||||
|
assignments. A successful completed calculation automatically replaces them;
|
||||||
|
no preview/apply step is introduced.
|
||||||
|
- A valid solution may be applied when the time limit expires even if optimality
|
||||||
|
has not been proven.
|
||||||
|
- Preserve the existing scheduling input revision check. A result based on
|
||||||
|
outdated inputs must not replace the current assignments.
|
||||||
|
- Failed, infeasible, interrupted, stale and no-solution calculations preserve
|
||||||
|
existing assignments.
|
||||||
|
- Report success only after the resulting assignments have been saved. Keep
|
||||||
|
status and saved results consistent.
|
||||||
|
|
||||||
|
## Server-sent events and connection recovery
|
||||||
|
|
||||||
|
- Use server-sent events (SSE) for backend-to-frontend status updates.
|
||||||
|
- On initial connection and reconnection, provide the current backend status.
|
||||||
|
Correctness must not depend on receiving every previous event.
|
||||||
|
- Maintain updates across navigation within the application so completion
|
||||||
|
notifications can appear outside the show page.
|
||||||
|
- If the connection is lost, indicate that displayed status may be outdated
|
||||||
|
while the backend calculation continues. Reconnect and reconcile with the
|
||||||
|
current status when connectivity returns.
|
||||||
|
- Configure the application's proxy for streaming so updates reach the client
|
||||||
|
promptly rather than being buffered until completion.
|
||||||
|
|
||||||
|
## Completion notifications
|
||||||
|
|
||||||
|
- Show an application-wide snackbar when a calculation completes or fails,
|
||||||
|
including when the user has navigated to another application page.
|
||||||
|
- Include the show name, a short outcome and a View show action.
|
||||||
|
- Phase changes update progress without generating snackbars.
|
||||||
|
- After temporary connection loss, show a missed completion notification once
|
||||||
|
when the connection recovers. Reconnection must not repeatedly notify for
|
||||||
|
the same completion.
|
||||||
|
- Do not replay old snackbars on page reload or reopening the application;
|
||||||
|
show the retained status on the show page instead.
|
||||||
|
- Email, browser notifications and notifications outside the application are
|
||||||
|
outside S12.
|
||||||
|
|
||||||
|
## Persistence and backend restarts
|
||||||
|
|
||||||
|
- Retain the latest scheduling status and outcome across backend restarts,
|
||||||
|
aligned with the PostgreSQL persistence specified in
|
||||||
|
`S16_store-state-in-persistent-storage`.
|
||||||
|
- Calculations interrupted by a backend restart become recognizably Interrupted
|
||||||
|
rather than remaining Running indefinitely. Do not resume them automatically;
|
||||||
|
allow the user to start again.
|
||||||
|
- Previously saved results survive restart. Volatile in-memory status alone
|
||||||
|
does not satisfy S12; its implementation must integrate with S16 storage.
|
||||||
|
- Target the single active backend instance defined by S16. Distributed
|
||||||
|
execution and scheduling on another PC remain in S13.
|
||||||
|
|
||||||
|
## Out of scope
|
||||||
|
|
||||||
|
- Cancelling a calculation or applying an intermediate solution.
|
||||||
|
- History of earlier calculations beyond the latest status and outcome.
|
||||||
|
- Global capacity limits, queues and remote workers.
|
||||||
|
- Changes to scheduling objectives or constraints.
|
||||||
|
- This specification grants no coding-standards waiver.
|
||||||
|
|
||||||
|
## Acceptance criteria
|
||||||
|
|
||||||
|
- [ ] Starting Schedule Groups returns without waiting for solver completion;
|
||||||
|
leaving or reloading the page does not interrupt the calculation.
|
||||||
|
- [ ] Opening a show in another screen recovers its current backend status;
|
||||||
|
duplicate runs for the same show are prevented in frontend and backend,
|
||||||
|
while different shows can run concurrently.
|
||||||
|
- [ ] Running status shows elapsed time, phase and discovery of a valid solution
|
||||||
|
during a phase, without a fabricated completion percentage or ETA.
|
||||||
|
- [ ] SSE delivers status changes promptly through the deployed proxy. Initial
|
||||||
|
connection and reconnection reconcile the current state, and loss of
|
||||||
|
connectivity visibly marks status as potentially outdated.
|
||||||
|
- [ ] Successful runs automatically apply their result after the existing start
|
||||||
|
confirmation, retain stale-input protection and distinguish proven optimal
|
||||||
|
results from valid results at the time limit.
|
||||||
|
- [ ] The final display includes finish time and concrete attendance, spread and
|
||||||
|
variety results when successful; unsuccessful outcomes are distinguishable
|
||||||
|
and explain that previous assignments were preserved.
|
||||||
|
- [ ] An application-wide snackbar reports completion or failure with the show
|
||||||
|
name and View show action, including after navigation to another page.
|
||||||
|
- [ ] Connection recovery notifies once for a missed completion; phase changes,
|
||||||
|
repeated reconnection and reopening do not replay old snackbars.
|
||||||
|
- [ ] The latest status and outcome survive navigation, reload and backend
|
||||||
|
restart through persistent storage integrated with S16.
|
||||||
|
- [ ] After backend restart, interrupted calculations are marked Interrupted,
|
||||||
|
do not resume automatically and can be started again; saved results remain.
|
||||||
|
|
||||||
|
## Implementation handoff
|
||||||
|
|
||||||
|
This specification records the agreed design and behavior. Backend and frontend
|
||||||
|
changes, persistence integration, proxy configuration and validation are
|
||||||
|
subsequent implementation work. S12 replaces S9's synchronous request behavior
|
||||||
|
while retaining the existing scheduling and result-application protections.
|
||||||